What Goes Into a Bill of Quantities, and Where the Estimating Hours Go

It is Thursday afternoon, the tender goes back on Monday at noon, and the bill of quantities runs to 140 pages. Somewhere in section 3 there is a single line that reads “Demolish existing building, Item”. Everything the estimator knows about that building, its asbestos, its basement, the steel frame that may or may not be worth anything, has to be priced into that one line.

A bill of quantities (BoQ) is a list of everything that makes up a construction job, with each item described, measured and given a unit, so that every tendering contractor prices exactly the same scope. RICS defines it in NRM2 as “a list of the items that make up the component parts of a building, with detailed identifying descriptions and quantities”. Once the contract is signed, the bill becomes a contract document and its rates are used to value interim payments and variations.

What is a bill of quantities for?

Two jobs. Before contract, it lets several contractors price the same design without each of them measuring it from scratch, which is wasteful and produces bids nobody can compare. After contract, it becomes the yardstick. When the client adds a floor of soft strip or the engineer changes the propping, the bill rates are where the valuation of that change starts.

That second job is the one people forget at tender. A rate you shaded on Friday to win the work is the rate you will be paid for every variation for the next nine months. If you have read our piece on how variation orders are valued, you will know how quickly a thin rate compounds.

What sections does a bill of quantities contain?

NRM2 sets out the usual composition. Demolition packages often arrive with a much shorter set, but this is the full list:

  • Form of tender
  • Summary
  • Preliminaries
  • Measured works
  • Non-measurable works, including provisional sums and contractor-designed works
  • Risks, as a schedule of construction risks the client wants to transfer
  • Credits for materials arising from the works
  • Dayworks (provisional)
  • Annexes

Most of the pages are measured works. Most of the money risk sits in the sections after it.

A worked example from a demolition and strip-out bill

Here is a simplified extract of the kind of bill a demolition contractor might receive for an office block coming down to slab. It is illustrative and not NRM2-coded, and the rate column is empty because filling it is the estimator’s job.

RefDescriptionQtyUnitRate£
3.1Soft strip: remove suspended ceiling grid and tiles, all floors1,850m²
3.2Soft strip: lift and remove carpet tiles and underlay1,720m²
3.3Strip out redundant small power and lighting installations, all floors1Item
3.4Demolish three-storey steel-framed office building to top of ground floor slab; materials arising to become the contractor’s property1Item
3.5Break out and remove external hardstanding, 150mm thick420m²
PS1Defined provisional sum: removal of asbestos-containing materials identified in the refurbishment and demolition surveySet by client QS
R1Risk: unrecorded basement voids or underground tanks1Item
C1Credit: recovered structural steeltCredit

Look at line 3.4. One item, one price, and it carries the whole method: plant, propping, sequence, waste and the number of weeks on site. The measured lines above it are easy by comparison. An experienced estimator spends minutes on 3.1 and most of a day on 3.4.

Who prepares the bill, and who prices it?

On a traditional lump-sum job the client’s quantity surveyor prepares the bill. It can be firm, for a fully designed project priced to a lump sum, or approximate, where the quantities are remeasured as the work is done. On design and build the client issues its requirements and the contractor, or more often its package subcontractors, do the quantifying. NRM2 sets this out in a table, and the consequence for a demolition subcontractor on a design and build job is blunt. Nobody has measured anything for you.

Approximate bills deserve more caution than they get. The quantities will move, which sounds like protection, yet the descriptions are fixed, and a rate built around one method will not always survive a much larger quantity.

Pricing the bill: where the hours go

Watch an estimator price a bill and the time falls into two places. The first is take-off and checking, which means reading the drawings and the survey against the bill, finding what the QS missed and writing the queries before the deadline for them closes. The second is rate build-up, where each line turns into labour, plant, materials, waste and margin, and where a demolition estimator is mostly drawing on memory of the last job that looked like this one.

Both are slow and both repeat from tender to tender, which makes them good candidates for automation. The result we can point to is in estimating: a UK construction and fit-out contractor of circa £30m turnover cut its estimating time per bid by 60–70% and narrowed the variance between estimated and delivered cost. The detail is in the case study, and the demolition side of the argument is in AI demolition estimating.

What did not get faster was judgement. Someone still has to decide whether that steel frame is coming down in a fortnight or five weeks.

Provisional sums, risks and credits

A provisional sum covers work that is anticipated but not yet designed. NRM2 splits them into defined and undefined. For a defined sum the bill has to give the nature of the work, how and where it fixes to the building, a quantity showing its extent and any specific limitations, and the contractor is then assumed to have allowed for it in programme and preliminaries. For an undefined sum, no such allowance is assumed. On a demolition job that difference is real money. If the asbestos removal is a defined provisional sum and the licensed works run three weeks longer than anyone expected, the programme impact may be yours. Our breakdown of asbestos and demolition costs shows where that money tends to go.

The risk section is where the client lists residual risks it wants to transfer, and the contractor prices a lump sum for taking each one on. That premium is paid whether the risk materialises or not, so price it the way an insurer would.

Credits are the demolition-specific section. NRM2 lets the client ask the contractor to offer a credit for materials arising from strip-out or demolition, such as steel, copper, plant and fittings. Offer too much and you have bought scrap at today’s price for a building that will not be on the ground for months.

What can be automated in a bill of quantities?

More than most commercial teams assume. Measurement from drawings and models is increasingly automated, and so is matching bill descriptions to a library of past rates. Checking a bill against the survey and drawings, to find the items that are missing rather than the ones that are mispriced, is where we see the most wasted hours, and a well-built tool can do that overnight.

Method stays human. A tool can tell you how long the last few steel-framed offices took to bring down. It cannot tell you that this one backs onto a hospital and the Section 61 consent will cap your breaker hours. If you are comparing tools, our guide to construction estimating software sets out what to look for.

Bill of quantities FAQs

Is a bill of quantities a contract document?

Usually, yes. Once the contract is entered into, NRM2 treats the bill as the basis for valuing interim payments and varied work.

What does BoQ mean in construction?

Bill of quantities. Same thing, shorter.

What is the difference between a bill of quantities and a schedule of works?

A bill is measured, so every item carries a quantity and the tender total is the sum of quantity times rate. A schedule of works lists what needs doing, often room by room or trade by trade, and leaves the contractor to work out how much. Refurbishment and smaller demolition packages tend to arrive as schedules, which moves the measurement risk onto whoever prices them.

Is there a standard bill of quantities template?

Partly. The NRM2 appendices include templates for preliminaries pricing schedules, elemental pricing summaries, and provisional sums, risks and credits. The measured sections follow the work section structure in the rules themselves.

Who measures a bill for a demolition-only job?

Often nobody. Plenty of demolition packages go out with a scope, a survey and a set of drawings, and the contractor builds its own quantities from scratch before it can price anything.

If your estimators are spending weekends on take-off, book a discovery call and we will look at where the hours are going. Demolition contractors can see how we work with firms like theirs on our demolition operational efficiency page.

Pick the problem that’s holding your business back.

We put the fix into the systems you already run, on your own data. Fixed price, live in weeks, and it pays for itself before you add the next one.

Book a 30-minute fix callOr see what Fusion does and more insights.

Got this problem on your jobs?

Book a 30-minute fix call. Bring one real problem and we’ll tell you whether and how we’d fix it.

  • Fixed price, agreed in writing
  • Live in weeks, on your own jobs
  • Works with the systems you already run
Book a 30-minute fix call