A Demolition Price Is Only as Good as the Survey Under It

Two contractors price the same 1960s office block. One comes back well under the other and wins. Six months later the winner is arguing about asbestos lagging in the service risers that was in the survey all along, on page 41, in a section the estimator never reached before the deadline.

To price a demolition job, a contractor turns a survey, a set of drawings and a site visit into a method, then costs that method line by line: the strip-out, the hazardous materials, the structure, the waste, the plant, the time on site and the constraints that limit how fast any of it can happen. Most of the gap between those two prices was decided before anyone opened a spreadsheet.

How do you price a demolition job?

Here is the order we would work through it, step by step, and where the money tends to go missing at each stage.

Step 1: Read the survey before the drawings

The refurbishment and demolition survey is the most expensive document in the tender pack to skim. It tells you which hazardous materials are where. Just as important, it tells you which areas the surveyor could not get into, and those caveats are scope. An inaccessible roof void listed as “presumed” has to be priced, qualified or argued about later. Our piece on what a refurbishment and demolition survey should tell a contractor goes through the report section by section, and asbestos and demolition costs covers how the removal gets priced.

Step 2: Price the soft strip as its own job

Soft strip is labour-heavy, slow and full of surprises above the ceilings. Folding it into one demolition rate hides the part of the job where productivity varies most. Price it floor by floor, keep the hazardous strip apart from the general strip, and write down what you have assumed about access and lifts. There is more on this in how much of a soft strip you can price before you open a ceiling.

Step 3: Follow every tonne to the gate

Waste is where demolition prices drift quietly. Concrete and masonry might be crushed and reused on site, or all of it might leave in wagons, and those are very different numbers. Mixed waste, hazardous waste, metals and timber each have their own route, receiving site and paperwork. Work out tonnages per stream from the survey and the drawings, then price the haulage and gate fees for each stream separately. The waste transfer note post covers the documents that travel with each load.

Step 4: Build the plant list from the method

A common mistake is pricing the machines the yard has free instead of the machines the method needs. A high-reach for a six-storey frame, a smaller excavator with a pulveriser for the slab, a crusher if the arisings are staying on site. Each needs a hire or internal rate, transport, fuel and a number of weeks on site. Then check those weeks against the programme, because a machine standing idle for a fortnight between phases still costs money. What plant management software should track explains why that idle time is so often invisible until the job closes.

Step 5: Price the hours you are allowed to work

Working hours, noise limits, dust and vibration monitoring, road closures, a school next door. Any one of them can cut the productive day hard. If the job needs a Section 61 consent, the conditions agreed with the local authority will shape which breakers you can run and when, and that flows straight into the programme. See what goes into a Section 61 application. The council’s response to a Section 80 demolition notice can bring conditions of its own, and our Section 80 post covers the timing.

Step 6: Credit the salvage, carefully

Structural steel, copper cable, aluminium window frames, sometimes whole items of plant. A salvage credit can win a tender. It can also lose money when the price assumed at tender has fallen by the time the steel is on the ground. Be conservative, and if the client’s bill asks for a credit against a list of materials, price what the survey lets you verify rather than what the building might contain.

Step 7: Put a real programme behind the preliminaries

Preliminaries on a demolition job are mostly time: site management, welfare, hoarding, security, monitoring and insurance. Get the duration wrong and the prelims are wrong with it. Build the programme from the method, phase by phase, and price the prelims off that programme. Our explainer on the construction programme of works covers how to lay one out.

Step 8: Decide what is contingency and what is a qualification

Some unknowns belong in the price and others belong in the tender letter. An unsurveyed basement is a qualification. The chance that the soft strip runs a week over is contingency. Where the client’s bill uses provisional sums, check whether they are defined or undefined, because under NRM2 that decides whether the programme impact is assumed to be in your price. We go through how that works in what goes into a bill of quantities.

Why do demolition quotes for the same building vary so much?

Different methods, mostly. One contractor plans to crush on site and another to cart everything away. One has read the survey caveats as excluded and another has priced them in. One has assumed working hours that the Section 61 conditions will never allow, and one has offered a steel credit that only works if scrap prices hold for six months. Put the quotes side by side and ask each bidder how the building is coming down; the answers usually explain the numbers.

What does demolition cost per m²?

There is no figure worth quoting without the building in front of you. Rates per square metre do get published, and they are fine for a feasibility budget, yet they are not a tender price. A two-storey timber-framed building on an open site and a four-storey concrete frame with asbestos in the risers and a railway along one boundary can share a floor area and almost nothing else. The drivers in the steps above are what move the number, with hazardous materials, structure, waste route, access, working hours and salvage doing most of the work.

Where does the estimating time go?

Most of it goes into reading. Survey reports, drawings, site photographs and the client’s preliminaries all have to be read against each other before a method can be chosen, and that reading is the part AI-assisted estimating handles well, pulling quantities and hazards out of documents so the estimator spends the time on method. In construction estimating, a UK construction and fit-out contractor of circa £30m turnover cut its estimating time per bid by 60–70% and narrowed the variance between estimated and delivered cost, as set out in the case study. That result comes from construction and fit-out; we do not yet have an equivalent measured figure for demolition. The demolition version of the argument is in AI demolition estimating.

Demolition pricing questions

What should a demolition quote include?

The scope, the method, the programme assumptions, the exclusions and qualifications, and the price. If a quote does not say how the building is coming down, ask.

Is salvage value taken off a demolition quote?

Often, as a credit. Some clients ask for credits to be shown separately so they can compare them across bidders, which is the cleaner way to do it.

Should a demolition contractor price from a bill of quantities?

When there is one. Plenty of demolition packages arrive as a scope and a survey, and the contractor does its own measurement.

If your team is pricing demolition tenders from memory and old spreadsheets, book a discovery call. You can also see how we work with demolition contractors.

Pick the problem that’s holding your business back.

We put the fix into the systems you already run, on your own data. Fixed price, live in weeks, and it pays for itself before you add the next one.

Book a 30-minute fix callOr see what Fusion does and more insights.

Got this problem on your jobs?

Book a 30-minute fix call. Bring one real problem and we’ll tell you whether and how we’d fix it.

  • Fixed price, agreed in writing
  • Live in weeks, on your own jobs
  • Works with the systems you already run
Book a 30-minute fix call