What Does NRM2 Govern That NRM1 and NRM3 Don’t?

A demolition subcontractor opens a tender package from a main contractor and finds the bill marked “measured in accordance with NRM2”. The estimator has priced a hundred demolition bills and never once opened NRM2. That is normal. It is also why queries come back late, because half of what looks like missing scope is the measurement rules deciding where things live.

NRM2 is the RICS standard for detailed measurement of building works: the rules a quantity surveyor follows to measure and describe work in a bill of quantities, so that contractors can price it on a common basis. It is one of three volumes in the RICS New Rules of Measurement, and the only one written for the tender bill itself.

NRM1, NRM2 and NRM3: which one does what?

VolumeFull titleUsed forWhen
NRM1Order of cost estimating and cost planning for capital building worksOrder of cost estimates and elemental cost plansEarly design, before there is enough to measure in detail
NRM2Detailed measurement for building worksBills of quantities and quantified schedules of works for tenderWhen the design is ready to go out to contractors
NRM3Order of cost estimating and cost planning for building maintenance worksMaintenance and whole-life cost plansAlongside capital cost planning, and on into operation

The current editions were published in October 2021 and reissued by RICS in October 2022 as professional practice information, with no material change to the content. The NRM2 edition in use is effective from 1 December 2021. If a bill turns up “measured to SMM7”, it is working to the older Standard Method of Measurement that NRM2 replaced in 2013.

How is NRM2 organised?

In three parts. Part 1 is general: how measurement fits the RIBA Plan of Work, plus the symbols, abbreviations and definitions. Part 2 deals with the bill of quantities as a document, covering what it is for, how it is composed, what information the QS needs to prepare one and how it should be coded. Part 3 is most of the book, the tabulated rules of measurement, split into 41 work sections that run from preliminaries through to builder’s work in connection with services.

Part 2 is the bit contractors should read and mostly don’t. It holds the rules on provisional sums, risks and credits, and those are the clauses that decide who pays when something goes wrong on site.

Where does demolition sit in NRM2?

Two work sections matter most. Work section 3 covers demolitions. Work section 4 covers alterations, repairs and conservation, which is where a lot of strip-out and partial demolition on refurbishment jobs ends up. Work section 1, preliminaries, carries the site set-up, hoarding, temporary works and management costs that a demolition price leans on heavily.

A bill can also be laid out elementally, following the NRM1 group elements instead of the NRM2 work sections. In that layout, major demolition works and toxic or hazardous material treatment fall under group element 0, facilitating works, while minor demolition sits in external works. Same building, different places in the bill. If you are reconciling a tender against a cost plan, that is exactly where items go missing. Contractors in the sector can see how we approach this on our demolition operational efficiency page.

Defined and undefined provisional sums

This is the clause worth printing out. NRM2 says a provisional sum for defined work must come with four pieces of information: the nature and construction of the work, how and where it is fixed to the building, a quantity indicating its scope and extent, and any specific limitations. Where all of that is given, the contractor is assumed to have allowed for the work in its programme, planning and preliminaries. Where any of it is missing, the sum is treated as undefined, whatever the bill calls it, and no such allowance is assumed.

Picture a strip-out package with a “defined” provisional sum for removing asbestos insulating board from a plant room, and no quantity anywhere. Under NRM2 that is an undefined sum, and the time it takes is not yours to swallow in preliminaries. A commercial manager who knows the clause has a conversation with the QS. One who doesn’t has a loss.

How does NRM2 handle risk and salvage credits?

Residual risks the client wants to transfer go into a schedule of construction risks, and the contractor prices a lump sum for taking each one on. NRM2 is plain that the premium is paid whether or not the risk materialises. Risks the two sides share are usually handled as provisional quantities, with the contractor taking the pricing risk and the client keeping the quantity risk.

Credits are the section demolition contractors care about. The client can list materials arising from strip-out or demolition and invite a credit against each, or ask the contractor to propose its own list. NRM2 includes templates for provisional sums, risks and credits in an appendix, which is the closest the standard comes to a ready-made bill of quantities template.

Where does software fit?

Measurement standards are the reason estimating software can work at all. If every bill is coded to the same structure, rates from one job map onto the next, and a cost plan built to NRM1 can be reconciled line by line against a tender priced to NRM2. NRM2 gives a lot of space to codification for that reason.

Most contractors are not there yet. Bills arrive as PDFs, rates live in spreadsheets named after the job, and the coding is lost the moment someone retypes a description into their own template. Tools for tender management and estimating help only when the data underneath them is consistent. Our pieces on cost modelling and quantity surveying software go further into how that data gets reused.

NRM2 questions

Is NRM2 mandatory?

No. RICS publishes it as professional practice information, and a bill is measured to NRM2 because the tender and contract documents say so.

Has NRM2 replaced SMM7?

Yes, in 2013.

What is the difference between NRM1 and NRM2?

NRM1 is for estimating and cost planning while the design is still developing, working in elements and floor areas. NRM2 is for measuring a finished design in enough detail to tender it.

Where can I get NRM2?

From the RICS website, which has the 2021 edition and the appendix templates as downloads.

What is an elemental cost plan?

A cost plan structured by building element, following NRM1. It is what the QS uses to control cost before there is a bill, and the benchmark a tender gets checked against once there is one.

For a plain walk through the bill itself, start with what goes into a bill of quantities. If measurement and rate data are the bottleneck in your tendering, book a discovery call.

Pick the problem that’s holding your business back.

We put the fix into the systems you already run, on your own data. Fixed price, live in weeks, and it pays for itself before you add the next one.

Book a 30-minute fix callOr see what Fusion does and more insights.

Got this problem on your jobs?

Book a 30-minute fix call. Bring one real problem and we’ll tell you whether and how we’d fix it.

  • Fixed price, agreed in writing
  • Live in weeks, on your own jobs
  • Works with the systems you already run
Book a 30-minute fix call